Annual Construction Program and Project Status

An annual construction program is developed based on the 65km of sidewalk gaps identified. Please check the table below for updates. The most current year program may be tentative and subject to budget approval by Council


Street

Sidewalk side
(N,S,E,W)

Ward


Status

Sciberras Rd - Ferrah St to Lichfield Rd W
3
Design On-going
Sciberras Rd - Fred Varley Drive to 85 m north of Fred Varley Drive E,W
3
Design On-going
Laidlaw Blvd - Bullock Dr to Highway 7 E
4
Design On-going
Donald Cousens Parkway -  Major Mackenzie Dr E to 150 m south of Major Mackenzie Dr E W
5
Design On-going
Denison St - Birchmount Road to Clayton Drive N
8
Construction On-going
14th Ave - Woodbine to Rodick Rd S
8
Design On-going
Commerce Valley Dr E - Minthorn Blvd to Leslie Ave N
8
Design On-going
Highglen Ave - Kennedy Rd to Noble St N
8
Design On-going
Lee Ave - Kennedy Rd to Brimley Rd N,S
8
Design On-going
Minthorn Blvd - Commerce Valley Dr to 358 Minthorn Blvd S
8
Design On-going
Woodbine Avenue - Steeles Ave to 68 m north of Steeles Ave W
8
Design On-going
Yorktech Dr 232 Yorktech Dr to Woobine Ave
N
8
Design On-going

Last updated November 19, 2019