Project Updates as of September 23, 2021

Bayview Glen North

  • All new watermain and services installed 
  • Final restoration occurring Fall 2021

West Thornhill Phase 3A

(Morgan/Henderson)

  • All new storm sewers, watermain and services installed
  • Road reconstruction base completed, final restoration by end of September 2021
  • Final road top asphalt scheduled for Spring 2022

West Thornhill Phase 3B

(Johnson/Dove/Ida/Wiarton, St. Andres)

  • All infrastructure and services installed 
  • Johnson road reconstruction anticipated to be completed by early October 2021
  • All road resurfacing will be completed by November 2021

West Thornhill Phase 4A

(Royal Orchard/Knotty Pine/Kirk)

  • Sanitary and stormsewer progressing from Woodland Public School and going to Bayview
  • Sewer upgrades anticipated to rpogress through the winter and completion of infrastructure and road reconstruction anticipated Fall 2022
  • Knotty Pine and Kirk upgrades scheduled for 2022