UPDATE ON WEST THORNHILL STORMWATER FLOOD REMEDIATION - PHASE 2
September 20, 2016
Phase 2A construction of storm sewer and watermain works will continue through fall 2016 with base road restoration planned before the winter season.
March 31, 2016
A Community Information Meeting was held at the Thornhill Community Centre to present the West Thornhill Phase 2A flood control implementation. Road closures will be required to support the construction of storm sewer upgrades and water quality improvement works. Notices will be provided to residents throughout the 2016 construction period in advance of service disruptions.
November 12, 2013
The City of Markham is continuing field investigations to support storm sewer design in the Phase One and Phase Two improvement areas in West Thornhill. Phase One investigations will occur on Canadiana Drive and Phase Two investigations will occur within the area shown on the map below.
Field investigations include:
- topographic surveys,
- subsurface utility locates and marking, and
- drilling of boreholes to confirm soil conditions in future construction areas.
These field investigations will begin in November 2013 and continue through early December 2013.
Construction of storm sewer upgrades and associated watermain replacement is expected to begin in the Phase 2 area in 2016.
Learn more about the City's stormwater management and flood control strategies.
Phase 2 map is available upon request. Please email your request to Rob Muir, Manager of Stormwater at RMuir@markham.ca.